South Mall, South Quays, Donovan's Road, Melbourne Road, etc.
South Mall
Works Extent
Southern side of South Mall.
Objectives
- Provision of safe, high quality segregated cycle infrastructure along South Mall;
- Installation of bi-directional cycle lanes including all necessary traffic signals and pedestrians crossing;
- Amendments to parking, road lining and traffic signals as required.
Timeline
Start: Construction Phase Commenced Late 2020.
Finish: Works are now completed.
South Quays - Terence McSwiney, Albert Quay & Victoria Road
Works Extent
From Parnell Bridge to Victoria Road Junction with Centre Park Road.
Objectives
- Provision of safe, high quality dedicated cycle infrastructure between Docklands and the City Centre;
- Installation of inbound and outbound cycle lanes on the above roads;
- Amendments to parking, road lining and traffic signals as required.
Timeline
Start: Contractor appointed January 2021.
Finish: Works are now substantially complete.
Donovan's Road
Works Extent
From Donovan's Road to Magazine Road.
Objectives
- Provision of a shared surface to create a safer and enhanced travel experience for cyclists and other road users;
- Resurfacing of existing road surface and amendments to road markings as required.
Timeline
Start: Construction Phase commenced late (December) 2020.
Finish: The project is now substantially complete.
Melbourne Road/Rossa Avenue
Works Extent
From junction with Curraheen Road to junction with Model Farm Road.
Objectives
- Provision of safe, high quality dedicated cycle infrastructure along Melbourne Road;
- Installation of inbound and outbound cycle lanes on the above road;
- Amendments to parking, road lining and traffic signals as required.
Timeline
Start: Construction Phase commence early (January) 2021.
Finish: The work is now substantially complete.
Magazine Road to Glasheen Road LInk
Works Extent
Schoolboy's Lane from Magazine Road to Glasheen Road.
Objectives
- Upgrade and improve existing pathway through parkland to enhance user safety and experience;
- Install new surfacing to existing path;
- Install new public lighting and CCTV.
Timeline
Start: June 2021.
Finish: Works are now substantially complete.
Centre Park Road & Monahan's Road
Works Extent
Full length of Centre Park Road and Monahan Road.
Objectives
- Provide a safe inbound and outbound route between the Marina and Victoria Road;
- Installation of inbound and outbound cycle lane on the above roads;
- Amendments to parking, road lining as required.
Timeline
Works completed 2020.
Deanrock Junction
Works Extent
Junction of Vicars Road, Togher Road and Clashduv Road.
Objectives
- Improve safety of junction;
- Replace existing traffic island and pedestrian crossings;
- Re-surface road and replace road markings;
- Replace footpath surface;
- Replace traffic signals.
Timeline
Works completed 2020.
For further information please contact John Stapleton, Senior Engineer at email john_stapleton@corkcity.ie