Curraheen Road Pedestrian and Cycle Safety Improvement Scheme

Planning/Design Phase

Works Extent

Curraheen Road from west of Melbourn Road to Junction with N40.

Objectives

  • Upgrade of the existing pedestrian crossing located at Scoil an Spioraid Naoimh and installation of new Toucan crossing at Curraheen Walkway;
  • Installation of upgraded pedestrian crossing facilities, including raised tables and tactile crossing points at side road junctions along Curraheen Road between Bridgefield Grove and Melbourn Road;
  • Improvement works to the Rossa Avenue junction incorporating pedestrian and cycle safety measures;
  • Installation of segregated cycle lanes;
  • Adjustments to the existing road layout, including lining, parking, etc.
  • Enhancement to the existing facilities on Rossa Avenue.

Timeline

Start: Design Phase Commenced September 2021.

Finish: Section 38 approved early 2022 with Detailed Design ongoing.

Curraheen Rd Ped Cycle pic 1 of 2

Curraheen Rd Ped Cycle 2 of 2