Programme
| Indicative Programme to Completion | |
| May 2018 | Final Funding Sanction |
| July 2018 | Commence Construction |
| Sept. 2018 | Complete Services Diversions |
| February 2019 | Complete Steelwork in lower harbour |
| February 2019 | Complete Construction of Abutments |
| March 2019 | Bridge Transportation by barge and lift onto abutments |
| April 2019 | Complete Construction |
| May 2019 | Official Bridge Opening |