Indicative Programme to Completion
May 2018 Final Funding Sanction
July 2018 Commence Construction 
Sept. 2018 Complete Services Diversions
February 2019 Complete Steelwork in lower harbour
February 2019 Complete Construction of Abutments
March 2019 Bridge Transportation by barge and lift onto abutments 
April 2019 Complete Construction
May 2019 Official Bridge Opening