Programme

 

Indicative Programme to Completion
May 2018Final Funding Sanction
July 2018Commence Construction 
Sept. 2018Complete Services Diversions
February 2019Complete Steelwork in lower harbour
February 2019Complete Construction of Abutments
March 2019Bridge Transportation by barge and lift onto abutments 
April 2019Complete Construction
May 2019Official Bridge Opening