Programme
Indicative Programme to Completion | |
May 2018 | Final Funding Sanction |
July 2018 | Commence Construction |
Sept. 2018 | Complete Services Diversions |
February 2019 | Complete Steelwork in lower harbour |
February 2019 | Complete Construction of Abutments |
March 2019 | Bridge Transportation by barge and lift onto abutments |
April 2019 | Complete Construction |
May 2019 | Official Bridge Opening |