Curragh Road Scheme

Curragh Rd Scheme pic 1 of 2
Projects Completed

Works Extent

Junction improvement works at the Curragh Road, Kinsale Road, Pearse Road, Green Lawn junction; and at the Tory Top Road, Pearse Road junction.

Objectives

  • Improved facilities for pedestrians, cyclists and public transport users, while providing for the efficient movement of vehicular traffic.
  • Enhanced accessibility for pedestrians to local shops and other services, as well as public transport;
  • Reduction in road widths to be traversed by pedestrians and provision of safer pedestrian crossing;
  • Upgraded cycling facilities in the area.

Timeline

Start: Construction commenced in Q3 2022

Finish: Construction completed in Q1 2023. 

For further information please contact Kevin Gallagher, Senior Executive Engineer at email: kevin_gallagher@corkcity.ie